SEC-02 Risk Management Policy
Version 1.0 · Effective November 13, 2026 · THERCSGROUP PTE. LTD. (trading as SmartAlex, Singapore Reg. No. 202543608D)
Owner: Liam Webb. This policy is reviewed at least once a year under rule 1.10.
Purpose
This policy sets how we find, score, treat and accept security risks. It makes sure the biggest risks get attention first, and that nobody accepts a risk above their authority.
Scope
This policy covers risks to client data and to the service from our architecture, software, operations, suppliers, people, AI systems and legal duties.
Definitions
| Term | Meaning |
|---|
| Risk | Something that could harm client data or the service, scored by how likely it is and how much harm it would do. |
| Residual risk | The risk that remains once its controls are in place. |
| Risk owner | The person responsible for treating a risk by its due date. |
| Risk register | The single list of risks, with each risk's score, owner, treatment and due date. |
Roles and responsibilities
| Role | Who | Responsible for |
|---|
| Security lead | Liam Webb | Keeps the risk register and may accept a medium residual risk. |
| Risk owner | Named for each risk | Treats the risk by its due date and may accept a low residual risk. |
| Two directors | Any two directors | Accept a high residual risk, in writing. |
| Directors | The board | See the risk register in the January security report. |
Rules
| Rule |
|---|
| 2.1 | The security lead keeps one risk register. Each risk has an owner, a treatment and a due date. It is scored for likelihood and for impact from 1 to 5, and its score is the two multiplied. |
|---|
| 2.2 | A score of 1 to 4 is low, 5 to 9 is medium, 10 to 14 is high and 15 to 25 is critical. |
|---|
| 2.3 | Each risk is treated in one of four ways. We reduce it with a control, accept it, transfer it through insurance or a contract, or stop the activity that causes it. |
|---|
| 2.4 | The risk owner may accept a low residual risk. The security lead may accept a medium residual risk. A high residual risk is accepted only by two directors in writing. A critical risk is never accepted. |
|---|
| 2.5 | Every new system, supplier and major feature is assessed for risk before it goes live, as part of the security check in SEC-04. |
|---|
| 2.6 | The register is reviewed every quarter, after every serious incident and after every significant change. The directors see the register in the January security report. |
|---|
How a risk is handled
Each risk goes through the same five steps.
| Step | What happens | Led by |
|---|
| 1. Find | Risks come from the security check on every new system, supplier and major feature, and from incidents, changes and the quarterly review. | Anyone, through the security lead |
| 2. Score | Likelihood and impact are each scored from 1 to 5, and the risk's score is the two multiplied. | Security lead |
| 3. Treat | We reduce the risk with a control, accept it, transfer it through insurance or a contract, or stop the activity that causes it. | Risk owner |
| 4. Accept | Whatever risk remains is accepted only by the person allowed to accept it, as the table below shows. | See the table |
| 5. Review | The register is reviewed every quarter, after every serious incident and after every significant change. | Security lead |
Risk levels and who may accept them
| Score | Level | Who may accept the residual risk |
|---|
| 1 to 4 | Low | The risk owner. |
| 5 to 9 | Medium | The security lead. |
| 10 to 14 | High | Two directors, in writing. |
| 15 to 25 | Critical | Nobody. A critical risk is never accepted. |
How we check this policy is followed
| Check | How often | Record |
|---|
| The risk register is reviewed. | Every quarter, and after every serious incident or significant change | Risk register |
| The directors see the register. | Every January | Security report |
| Each new system, supplier and major feature is assessed. | Before it goes live | Security check under SEC-04 |
| The owner checks that this policy is followed and keeps it current. | At least once a year | Version history of this pack |
Exceptions
An exception to this policy is handled under rule 1.9. It is written down with the reason, the risk, the control that makes up for it and an end date within 90 days. The security lead approves it, and a director also approves it when the risk is high.
Breaking this policy
Rule 1.13 applies. Breaking a policy can lead to retraining, loss of access, a written warning, the end of employment or a contract, or legal action.
Related documents
| Document | What it holds |
|---|
| Risk register | Every risk, with its score, owner, treatment and due date. |
| SEC-04 and SEC-18 | The security check on new systems and features, and incidents that add new risks. |