Purpose

This policy sets how we find, score, treat and accept security risks. It makes sure the biggest risks get attention first, and that nobody accepts a risk above their authority.

Scope

This policy covers risks to client data and to the service from our architecture, software, operations, suppliers, people, AI systems and legal duties.

Definitions

TermMeaning
RiskSomething that could harm client data or the service, scored by how likely it is and how much harm it would do.
Residual riskThe risk that remains once its controls are in place.
Risk ownerThe person responsible for treating a risk by its due date.
Risk registerThe single list of risks, with each risk's score, owner, treatment and due date.

Roles and responsibilities

RoleWhoResponsible for
Security leadLiam WebbKeeps the risk register and may accept a medium residual risk.
Risk ownerNamed for each riskTreats the risk by its due date and may accept a low residual risk.
Two directorsAny two directorsAccept a high residual risk, in writing.
DirectorsThe boardSee the risk register in the January security report.

Rules

Rule
2.1The security lead keeps one risk register. Each risk has an owner, a treatment and a due date. It is scored for likelihood and for impact from 1 to 5, and its score is the two multiplied.
2.2A score of 1 to 4 is low, 5 to 9 is medium, 10 to 14 is high and 15 to 25 is critical.
2.3Each risk is treated in one of four ways. We reduce it with a control, accept it, transfer it through insurance or a contract, or stop the activity that causes it.
2.4The risk owner may accept a low residual risk. The security lead may accept a medium residual risk. A high residual risk is accepted only by two directors in writing. A critical risk is never accepted.
2.5Every new system, supplier and major feature is assessed for risk before it goes live, as part of the security check in SEC-04.
2.6The register is reviewed every quarter, after every serious incident and after every significant change. The directors see the register in the January security report.

How a risk is handled

Each risk goes through the same five steps.

StepWhat happensLed by
1. FindRisks come from the security check on every new system, supplier and major feature, and from incidents, changes and the quarterly review.Anyone, through the security lead
2. ScoreLikelihood and impact are each scored from 1 to 5, and the risk's score is the two multiplied.Security lead
3. TreatWe reduce the risk with a control, accept it, transfer it through insurance or a contract, or stop the activity that causes it.Risk owner
4. AcceptWhatever risk remains is accepted only by the person allowed to accept it, as the table below shows.See the table
5. ReviewThe register is reviewed every quarter, after every serious incident and after every significant change.Security lead

Risk levels and who may accept them

ScoreLevelWho may accept the residual risk
1 to 4LowThe risk owner.
5 to 9MediumThe security lead.
10 to 14HighTwo directors, in writing.
15 to 25CriticalNobody. A critical risk is never accepted.

How we check this policy is followed

CheckHow oftenRecord
The risk register is reviewed.Every quarter, and after every serious incident or significant changeRisk register
The directors see the register.Every JanuarySecurity report
Each new system, supplier and major feature is assessed.Before it goes liveSecurity check under SEC-04
The owner checks that this policy is followed and keeps it current.At least once a yearVersion history of this pack

Exceptions

An exception to this policy is handled under rule 1.9. It is written down with the reason, the risk, the control that makes up for it and an end date within 90 days. The security lead approves it, and a director also approves it when the risk is high.

Breaking this policy

Rule 1.13 applies. Breaking a policy can lead to retraining, loss of access, a written warning, the end of employment or a contract, or legal action.

Related documents

DocumentWhat it holds
Risk registerEvery risk, with its score, owner, treatment and due date.
SEC-04 and SEC-18The security check on new systems and features, and incidents that add new risks.